Create, Edit, and Delete Planning Elements — Activities and Milestones

In InLoox, a project plan consists of activities (shown as bars in the Gantt chart) and milestones (shown as diamond shapes). Multiple activities can be grouped into summary activities.

Types of Planning Elements

  • Activity — A single task or work package with a defined start date, end date, and duration.
  • Summary Activity — A parent element that groups multiple activities together. Its duration is automatically calculated from the child elements.
  • Milestone — A significant event or checkpoint in the project schedule. Milestones have only a date and no duration.

Create Activities and Milestones

  1. Open InLoox Web App and navigate to your project.
  2. Click on the Planning tab — the planning list appears on the left and the Gantt chart on the right.
  3. To add an activity, click New Activity. To add a milestone, click New Milestone.
  4. Enter a title for the new element. If you don't set start or end dates, InLoox schedules the element based on the project's creation date. Activities default to a one-day duration (8 work hours).
tip

You can also convert an activity into a milestone (and vice versa) by right-clicking the element and selecting the conversion option in the context menu.

Edit Planning Elements

To edit an activity or milestone:

  1. Click the element in the planning list or Gantt chart.
  2. Click the pencil icon next to the element name, or right-click and select Edit.
  3. A side panel opens where you can change the name, duration, start/end dates, constraints, resources, and other attributes.

Create Summary Activities

Summary activities group several related activities together:

  1. Create the individual activities first.
  2. Select the activities you want to group (hold Ctrl to select multiple).
  3. Use the Indent button in the toolbar (or right-click and select Indent) to nest the selected activities under a parent element, which becomes the summary activity.

The summary activity's duration automatically spans from the earliest start date to the latest end date of its child activities.

Create Sub-Activities

To create a sub-activity within a summary activity:

  1. Select the summary activity under which you want to add a child element.
  2. Click the Add button or use the keyboard shortcut.
  3. The new activity is added as a child element of the selected summary activity.

Change the Order of Planning Elements

You can reorder planning elements using drag and drop in the planning list. Simply click and drag an element to its new position.

Delete Planning Elements

To delete planning elements:

  1. Select one or more activities or milestones (hold Ctrl to select multiple).
  2. Right-click and choose Delete.
warning

Deleting a summary activity also deletes all of its subordinate activities. This action cannot be undone if auto-save is enabled.

Highlight Planning Elements

To visually highlight important planning elements, you can assign colors:

  1. Select one or more planning elements.
  2. Right-click and select Highlight from the context menu.
  3. Choose a color for the selected elements.

Highlighted elements are displayed with the chosen color in both the planning list and the Gantt chart, making important tasks immediately recognizable.